New DAQ validated in a long MANGO data-taking run; performance OK so far.
09:01
→
09:02
DavideP report1m
Speaker:
Davide Pinci(Istituto Nazionale di Fisica Nucleare)
Fantini company:
is asking for news about final designs;
a possible time slot to machine the copper is soon after Easter;
Bussetti was informed about the successful gas tightness test;
3 FanINFanOut confirmed at LNF
09:02
→
09:03
Elisabetta report1m
Speaker:
Elisabetta Baracchini(Istituto Nazionale di Fisica Nucleare)
09:03
→
09:04
DavideF report1m
Speaker:
Davide Fiorina(GSSI & INFN)
Weekly Summary
GEM stacks and assembly
The first GEM stack was successfully assembled at LNF, but an alignment issue was found between the inner and the external frames.
The agreed fix is to slot all external-frame holes by 2 mm per side on both GEM stacks.
Tecnoalarm will machine the modified parts, and Daniele will provide updated drawings by 23/03.
GEMs and cathodes from CERN
GEM3 showed critical issues: the v-bond created some short-circuited protection resistors.
CERN confirmed that new GEMs for the second stack will be shipped soon.
CERN is also remaking the cathodes; the team is ready to contribute 400 CHF, provided all edges/tips are rounded for safe 50 kV operation.
Copper box movement in Hall F
A Hall F inspection confirmed that the copper box can be transported already assembled into the experimental area.
The current plan uses a remote-controlled crane + mobile air cushion, with an estimated cost of about 5 k€.
DavideF must verify with SPP and LNGS Technical Coordination whether temporary removal of corridor wall sheets is allowed and what documentation is required.
Copper drawings
A way was found to unblock the copper drawing workflow after the stall.
Field cage, setup, and infrastructure
For the field cage, missing closure holes may be added using a dedicated punching tool designed by Daniele.
Work progressed on the pre-commissioning infrastructure, though some 30x30 Bosch aluminum profiles are still missing.
Other follow-up items
A broader Hall F inspection with the full team should be organized later, though it is not urgent.
DavideF still has to check HV cable compatibility in Hall F and discuss a possible thin PMT window solution with Giorgio.
The team should also check whether the second GEM shipment can use an already planned CERN transport on 01/04.
09:04
→
09:05
Giorgio report1m
Speaker:
Giorgio Dho(Istituto Nazionale di Fisica Nucleare)
Analysis
Main news is from Luan who will optimize digitization for quest high gain and low gain and fusion and has implemented Atul's variables to test ER/NR discrimination.
Analysis meeting on Thursday (presentation from Luan expected)
LNF
Per i PMT, come vogliamo testarli e validarli?
Chiedere a Luigi di scrivere per la modifica dei catodi (Farò appena dopo il meeting)
Altro
Mi hanno chiesto di fare il talk su dark matter direzionale a CSN2 ad aprile. Buona pubbicità
09:05
→
09:06
Stefano report1m
Speaker:
Stefano Piacentini(GSSI and INFN LNGS)
09:06
→
09:07
Giulia report1m
Speaker:
Giulia D'Imperio(Istituto Nazionale di Fisica Nucleare)
dedicated simulations of the 8 keV xrays from GEM copper available on the cloud. Emanuele/DavideP will digi-reconstruct and analyze them.
Emanuele is investigating the possibility to use the cnaf queues from a dedicated cnaf account (instead of using the notebook)
09:07
→
09:08
Fabrizio report1m
Speaker:
Fabrizio Petrucci(Istituto Nazionale di Fisica Nucleare)
09:08
→
09:09
Andrea report1m
Speaker:
Andrea Messina(Istituto Nazionale di Fisica Nucleare)