Weekly Meeting

Europe/Rome
Davide Fiorina (GSSI & INFN)
    • 09:00 09:01
      Previous week recap 1m
      Speaker: Davide Fiorina (GSSI & INFN)

      Previous week recap (by person) — week of this meeting

      Davide P.

      • Confirmed trigger module commissioning readiness: Herman planned to assemble 50 Ω termination resistors this week.
      • Completed vessel validation tests: source flange + new O-ring, and 1/8" gas connectors up to +3 mbar.
      • Reported 3DExperience permission issues still impacting copper-box drawings closure.

      Davide F.

      • Humidity sensor procurement blocked by supplier incompatibility with Public Administration; alternative supplier search started.
      • O₂ sensor procurement still waiting for quote and required documents.
      • Copper-box drawings: 3DS issue solved; Antonio expected to provide final drawings this week.
      • Inner GEM frames retrofitted by Tecnoalarm; assembly test scheduled for tomorrow.
      • Rometec: first batch order submitted and under follow-up.
      • Hall F: inspection with technicians and LNGS services to finalize routing paths.
      • Water tanks transported to LNF; receipt/inspection pending.
      • Defined LN2 line requirement: continuous copper line (avoid SS + Swagelok approach).
    • 09:01 09:02
      DavideP report 1m
      Speaker: Davide Pinci (Istituto Nazionale di Fisica Nucleare)
      • Completed overpressure vessel validation tests. All ok up to +5 mbar.
    • 09:02 09:03
      Elisabetta report 1m
      Speaker: Elisabetta Baracchini (Istituto Nazionale di Fisica Nucleare)
    • 09:03 09:04
      DavideF report 1m
      Speaker: Davide Fiorina (GSSI & INFN)
      • O₂ sensor procurement: vendor said they will provide the required documents; no feedback received yet.

      • H₂O (humidity) sensor procurement: vendor said they will provide the required documents; no feedback received yet.

      • HV cable: quote requested from an Italian supplier.

      • NIER (PRA update): no feedback last week; I will re-ping them.

      • Frascati (tomorrow): meeting planned. I will stay for 3 days; goal is to mount the first GEM stack, assuming the remaining issues are solved.

      • Copper box movement: tomorrow Cesidio will provide feedback (if any) from the LNGS crane team to clarify the movement procedure.

      • Copper Box: review of Antonio's work in progress...

      • Trigger module test bench: postponed to next week.

      • Hall F: inspection with technicians and LNGS services to finalize routing paths; to be discussed and organized.

    • 09:04 09:05
      Giorgio report 1m
      Speaker: Giorgio Dho (Istituto Nazionale di Fisica Nucleare)
      • No real news from analysis.
      • Littleupdates from Igor on digitization and check with analysis.
      •  Today meeting with Edward Shields (Australian) and Federico (who won 3 months grant thanks to GSSI) to possibly improve  diffususion deconvolution
      • Premounting of GEMs looks ok with the bent bandelle. We will see when we try to mount
      • Field cage foils do not have the holes to secure it in position. Tomorrow we will try to understand how to deal with this
      • GEMs were repaired and are ready. Waiting for Luigi to understand how to bring them back
      • Paper on FC (Alex and myself): replying to reviews
    • 09:05 09:06
      Stefano report 1m
      Speaker: Stefano Piacentini (GSSI and INFN LNGS)
      • No reply from both contact persons for the Rb-83 source
      • Last week: DAQ meeting. Discussion about gas tightness tests results using N2 -> foreseen operation conditions 3+-2 mbar overpressure
      • New DAQ tested on a long data-taking in MANGO. Apparently everything ok so far. 
    • 09:06 09:07
      Giulia report 1m
      Speaker: Giulia D'Imperio (Istituto Nazionale di Fisica Nucleare)
    • 09:07 09:08
      Fabrizio report 1m
      Speaker: Fabrizio Petrucci (Istituto Nazionale di Fisica Nucleare)
    • 09:08 09:09
      Andrea report 1m
      Speaker: Andrea Messina (Istituto Nazionale di Fisica Nucleare)