Previous week recapSpeaker: Davide Fiorina (GSSI & INFN)
Previous week recap (by person) — week of this meeting
Davide P.
- Confirmed trigger module commissioning readiness: Herman planned to assemble 50 Ω termination resistors this week.
- Completed vessel validation tests: source flange + new O-ring, and 1/8" gas connectors up to +3 mbar.
- Reported 3DExperience permission issues still impacting copper-box drawings closure.
Davide F.
- Humidity sensor procurement blocked by supplier incompatibility with Public Administration; alternative supplier search started.
- O₂ sensor procurement still waiting for quote and required documents.
- Copper-box drawings: 3DS issue solved; Antonio expected to provide final drawings this week.
- Inner GEM frames retrofitted by Tecnoalarm; assembly test scheduled for tomorrow.
- Rometec: first batch order submitted and under follow-up.
- Hall F: inspection with technicians and LNGS services to finalize routing paths.
- Water tanks transported to LNF; receipt/inspection pending.
- Defined LN2 line requirement: continuous copper line (avoid SS + Swagelok approach).
- 2
-
3
Elisabetta reportSpeaker: Elisabetta Baracchini (Istituto Nazionale di Fisica Nucleare)
-
4
DavideF reportSpeaker: Davide Fiorina (GSSI & INFN)
-
O₂ sensor procurement: vendor said they will provide the required documents; no feedback received yet.
-
H₂O (humidity) sensor procurement: vendor said they will provide the required documents; no feedback received yet.
-
HV cable: quote requested from an Italian supplier.
-
NIER (PRA update): no feedback last week; I will re-ping them.
-
Frascati (tomorrow): meeting planned. I will stay for 3 days; goal is to mount the first GEM stack, assuming the remaining issues are solved.
-
Copper box movement: tomorrow Cesidio will provide feedback (if any) from the LNGS crane team to clarify the movement procedure.
-
Copper Box: review of Antonio's work in progress...
-
Trigger module test bench: postponed to next week.
-
Hall F: inspection with technicians and LNGS services to finalize routing paths; to be discussed and organized.
-
-
5
Giorgio reportSpeaker: Giorgio Dho (Istituto Nazionale di Fisica Nucleare)
- No real news from analysis.
- Littleupdates from Igor on digitization and check with analysis.
- Today meeting with Edward Shields (Australian) and Federico (who won 3 months grant thanks to GSSI) to possibly improve diffususion deconvolution
- Premounting of GEMs looks ok with the bent bandelle. We will see when we try to mount
- Field cage foils do not have the holes to secure it in position. Tomorrow we will try to understand how to deal with this
- GEMs were repaired and are ready. Waiting for Luigi to understand how to bring them back
- Paper on FC (Alex and myself): replying to reviews
-
6
Stefano reportSpeaker: Stefano Piacentini (GSSI and INFN LNGS)
-
7
Giulia reportSpeaker: Giulia D'Imperio (Istituto Nazionale di Fisica Nucleare)
-
8
Fabrizio reportSpeaker: Fabrizio Petrucci (Istituto Nazionale di Fisica Nucleare)
-
9
Andrea reportSpeaker: Andrea Messina (Istituto Nazionale di Fisica Nucleare)
-
1