2026 kick-off meeting
→
Europe/Rome
Agreed on the Tue 14.30 time slot (next meeting on the tenth of february)
Agreed on task list and assignments (see attached table)
Herman working on the NIM-TTL translation:
Purchase from mouser at GSSI failed -> purchase from CERN
16 channel upgrade is possible with a single module
Test with full DAQ light-sensor setup:
Waiting for latest connectors
PCIe board available (Herman’s office)
Event builder still missing -> mandatory for the commissioning
SC frontend:
HV modules and most of the SC -> extension of LIME software
New H and O sensors to be added to the SC system
Krypton source:
We need to investigate now if and how to purchase the source -> Luca taking care of contacting XENON/PTOLEMY
LNGS labs available to host the source wherever we buy it
Source very short lifetime -> coordination with commissioning schedule needed
Test on gas tightness:
Ongoing now (DavideP and DavideF)
Development of power supply box:
Presentation of status and drawings/connections to next WP5 meeting
Gas purification and low-radon filters:
Contact people working on this topic -> eventually drop it for the first part of the commissioning of CYGNO-04