Speaker:
Stefano Piacentini
(GSSI and INFN LNGS)
WP5 meeting organization
Tasks status and short-term to-do-list
-
Herman working on the NIM-TTL translation:
-
Test with full DAQ light-sensor setup:
-
Event builder still missing -> mandatory for the commissioning
-
SC frontend:
-
Krypton source:
-
We need to investigate now if and how to purchase the source -> Luca taking care of contacting XENON/PTOLEMY
-
LNGS labs available to host the source wherever we buy it
-
Source very short lifetime -> coordination with commissioning schedule needed
-
Test on gas tightness:
-
Development of power supply box:
-
Gas purification and low-radon filters: