Brief overview and summary of the Urania Construction & Commissioning progress. Key items addressed include: Status along schedule, Technical delivery evaluation, Key remaining items or milestones, Assessment of barriers to completion (if any), and Projected timeline to transition to Operations.
Slides for presentation
- Example summary slides from Giacomo Gallina (3/11/2024). Two Operations slides removed
Collection of supporting materials:
- Complete P6 extract (Gantt)
- Supporting formal reports (Draft status document)
- Online site design layout (AutoDesk visualizer)
Presentation of plans for Urania Operations
Operations Management Structure
- Roles and lines of authority
- Key supervisory positions
Draft slides from Henning Back.
Activities performed during routine plant operation
- Monitoring activities
- Maintenance activities
- UAr product shipment
- General facilities upkeep
All cost categories
Cost estimation
Supporting materials for cost estimation:
- Basis of estimate (BOE)
- Documentation of BOE (quotes to eng. judgment justification)
Current status (3/20/2024) provided in attached materials.
External review of Operations plan by individual(s) with relevant industry experience.
Assessment of Urania by agencies anticipated for the month of April 2024, time yet to be settled. Presence of industry expert(s) can provide valuable external input potentially via the anticipated meeting.
Presentation of plans for Urania Operations
Defining the criteria for the tart of Operations including:
- Technical Performance
- Operational
- Procedural
- Contractual
Draft documentation:
Document listing the plans and materials necessary for a smooth hand-off to routine operations. This includes operational details established and verified during Commissioning including:
- Staffing resources
- Plant performance parameters
- Shift schedule
Daily, weekly, monthly, etc. maintenance schedule to define the cadence of maintaining plant operations during the production period.
Risk Register for Urania (XLSX)
- Additional proposed Operations risks (Word)
--- Downstream requirements change
--- Plant failure due to maintenance schedule delays
--- Severe injury onsite
Details on the Carleton (Canada) supported effort to provide UAr shipping infrastructure and transport costs.
Contractual and legal aspects of operating a gas separation plant.
- Ownership
- Liability
- Oversight responsibility
- Training