Matteo Biassoni (Istituto Nazionale di Fisica Nucleare)13/01/2026, 11:00
Is Italy fully in charge of top, independent of the technical implementation (full WC, combined WC+panels, etc...)? will top have an independent DAQ?
Go to contribution page -
Karsten Heeger (Yale University)13/01/2026, 11:15
-
Donatella Tozzi (Istituto Nazionale di Fisica Nucleare), Giovanni Mazzitelli (Istituto Nazionale di Fisica Nucleare), Luigi Benussi (Istituto Nazionale di Fisica Nucleare)13/01/2026, 11:45
-
Karsten Heeger (Yale University), Penny L. Slocum (Yale University)13/01/2026, 14:15
Current status: - geometry detail, understanding of output, what's missing (inputs for simulations and simulations to take decisions)
Go to contribution page -
13/01/2026, 14:45
Is the current design for the single module the best/good enough? Which thickness? Do we need more measurements or can we freeze the design?
Go to contribution page -
13/01/2026, 15:05
Can we freeze the choice/start the procurement?
Go to contribution page -
13/01/2026, 15:25
Who is in charge of improving the mechanical coupling? Can the mechanical coupling be responsible for inefficiency of single tiles?
Go to contribution page -
13/01/2026, 15:45
Is the current choice the best? Is it scalable? Do we need to implement a different solution and do we have time to find one? Do we need to interact with CAEN to adapt to our needs (especially cabling/shielding)?
Go to contribution page -
13/01/2026, 16:15
-
James Wilhelmi (Yale)13/01/2026, 17:00
-
Matteo Biassoni (Istituto Nazionale di Fisica Nucleare)14/01/2026, 09:00
Procurement, QC, installation compatible with overall schedule. Focus on lateral and bottom (top only after CUPID deployment).
Go to contribution page
All material procured in single batch? Multiple batches? Need inputs to match QC and detector construction in the schedule -
14/01/2026, 09:30
What do we need to quality check? Do we need to characterize single tiles/panels? Single SiPMs? Assembled panels?
Go to contribution page
Where: - Yale? LNF? LNGS? - before/after assembly/shipment?
Who: - Yale? Yale + LNF? Technical staff? -
14/01/2026, 10:30
Who is in charge of installation? Yale technical staff? Need support from Italy?
Go to contribution page -
14/01/2026, 11:00
What do we need? Timeline?
Go to contribution page
Design and simulation report (start overleaf) - complete system
Technical design review of lateral and bottom shield - before starting procurement? Fix date?