Attendees: Giovanni Bencivenni, Gianluigi Cibinetto, Marco Pinamonti, Riccardo Pinamonti, Marco Poli Lener
o G. Cibinetto went through the project proposal underlining the main activities and goals.
o Then the contribution of Eltos has been addressed; the following agreement was found:
1. Eltos will produce 14-16 PCBs with strip readout (by September)
2. Eltos will produce 14-16 PCBs with pad readout (by September)
3. Eltos will produce 14-16 copper cathodes (by end of July)
4. Aluminum cathodes need more R&D and this activity will per excluded from the uRANIA project for the moment
The budget assigned to Eltos for items 1, 2 and 3 is 15 k€, this includes material, manpower and office costs.